The challenge

The customer had a state-of-the-art facility, perfect for developing new designs and technology. However, with more and more business coming in, the amount of working space had become an issue.

Our solution

Through a detailed consultation, we were able to get a full understanding of the clients’ needs and explore the building we were working on. From this, it became apparent that Norbar needed new offices and multi-levels to keep their testing processes efficient,

x1

double skin steel partitioning fitted

x2

mezzanine floors installed

14

week timeframe achieved

The results

By installing new mezzanine floors, we managed to double Norbar’s working space, and our efficient solution of double skin portioning helped us keep in line with the necessary timescale and budget. The finished facility will aid Norbar in their goal of achieving the highest level of innovation and precision in the field of torque tightening and measuring equipment.

“We were able to double the space by installing Mezzanine floors. The new zones were constructed using Double Skin Steel partitioning – a fast and efficient way to create a new separate space within a workplace of this type.”

Project Manager, PD Industrial

Timescale
14 weeks
Deliverables
  • Mezzanine floor
  • Project management
  • Onsite installation

And we can do the same for you.

Get in touch with our team to discuss your project requirements today.

More projects

We carried out this project under difficult circumstances but still delivered on time and within budget.

Trevor Deakin, - Operations Director, PD Industrial

This project demonstrated the importance of careful coordination and management of all construction-related activities, particularly when working on a fully operational site.

Brilliant from planning to execution. Phil managed CDM with no issues whatsoever, and orchestrated 8 different contractors to ensure no downtime.”

Aaron Cunningham, - Project manager, DHL

We had to be mindful that the site was still in operation with working staff. Our procedures were maintained in accordance with health and safety regulations