The challenge

When Primark were exiting an old premises they came to us as they knew we could complete the project in under 4 months or face large penalties by the landlord.

Our solution

We successfully executed a comprehensive CDM project, employing a combination of mechanical equipment and skilled manpower to dismantle a substantial quantity of pallet racking and an extensive multi-tier mezzanine floor.

120,000

pallet locations of racking removed

300,000

sqft of mezzanine floor removed

The results

The client was able to hand over the building on time without incurring any penalties.

It was a pleasure working with Primark and together we achieved a project others were not able to offer

Operations Director, PD Industrial

Timescale
4 months
Deliverables

Racking removal

Mezzanine removal

 