The challenge

Supply and fit racking within an 8 week window.

racking

The solution

We procured racking with a lead time of 3 weeks and efficiently constructed it using two teams, ensuring timely completion of the project.

12,000

pallet locations

8 Weeks

project completion time

The results

The outcome provided the client with additional pallet locations, enabling them to fulfil a new contract effectively.

Acting quickly is a strong point which is why we were able to deliver this project in 8 weeks.

Operations Director, PD Industrial

Timescale
5 weeks
Deliverables

Supply racking

Fit racking