B&M Middlewich — 2,820 Bays of Racking Strip-Out

B&M Middlewich — 2,820 Bays of Racking Strip-Out

B&M Middlewich — 2,820 Bays of Racking Strip-Out

Scale, Sequence and a Fixed Programme

Taking down 2,820 bays of racking is not simply a matter of manpower — it demands a controlled dismantling sequence, clear handling routes for frames and beams, and steady weekly progress against a fixed programme.

B&M's Middlewich site covers 47 double runs of racking, each with 60 bays. PD Industrial mobilised a dedicated team of six experienced installers to work through the site full time, following strict safety standards and a planned order of work that keeps materials organised as they come down.

How We Are Delivering It

The strip-out was broken into a clear sequence across the 47 double runs so the team can progress in an organised, efficient way. That controlled approach keeps the site safe, avoids bottlenecks in removal and stacking, and holds the project to the 10-week booking.

Project planning, on-site supervision and dismantling methodology are all managed in-house — the same model we use on multi-site retail programmes and large logistics strip-outs.

The Outcome

When the programme completes, B&M will have a cleared area at Middlewich ready for its next stage. The focus throughout is safe, efficient dismantling delivered on schedule.