Dilapidations
Primark — 120,000 Pallet Locations Removed in 4 Months

The Clock Was Already Running
When Primark came to PD Industrial, they already knew the stakes. They were exiting a major distribution centre and the lease clock was ticking. If the strip-out wasn't complete within four months, the landlord's penalty clauses would kick in — and for a project of this scale, the financial exposure was substantial.
This was not a straightforward dilapidations job. The figures alone make that clear: 120,000 pallet locations of racking to be dismantled, removed, and the floor reinstated. 300,000 square feet of multi-tier mezzanine floor to come down. All of it to be done safely, compliantly, and within a programme that most contractors wouldn't have quoted on.
The Scale of What PD Industrial Delivered
We mobilised a dedicated team combining mechanical equipment — critical for the efficient dismantling of large-scale mezzanine structures — with skilled installation operatives who could work safely at height and at pace.
The project was managed as a full CDM Principal Contractor scope. Method statements, risk assessments, a Construction Phase Plan, and daily site management were all produced and maintained in-house. There was no sub-contracting of the management function; PD Industrial's project team ran the site from mobilisation to final clearance.
The demolition sequencing was planned to allow multiple work fronts to progress simultaneously — the only way to move 300,000 square feet of mezzanine flooring and 120,000 pallet locations within four calendar months. Each work front had its own supervision, its own safety management, and its own daily programme targets.
Delivered. Penalty Avoided.
The site was cleared, reinstated, and handed back within the lease deadline. Primark avoided the penalty clauses. And PD Industrial demonstrated a capability that very few racking contractors in the UK can genuinely claim: the ability to mobilise, plan, and execute a strip-out at this scale within the kind of programme constraints that make lesser contractors reach for their exclusion clauses.
Related Projects
Dilapidations
Strip-OutRetail Distribution
B&M Middlewich — 2,820 Bays of Racking Strip-Out
Pallet RackingFood Retail & Cold Storage
Farmfoods — 30,000 Pallet Locations in 12 Weeks